Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity _________ should be crashed first, adding _________ to project cost.
A) B; $2,000
B) B; $8,000
C) C; $1,000
D) C; $2,000
E) C; $6,000
Correct Answer:
Verified
Q62: Which of the following statements regarding time-cost
Q62: An activity on a PERT network has
Q63: A project whose critical path has an
Q67: An activity on a PERT network has
Q76: A project being analyzed by PERT has
Q78: If an activity whose normal duration is
Q79: An activity on a PERT network has
Q80: Which of these statements regarding time-cost tradeoffs
Q97: Contract requirements state that a project must
Q125: A network has been crashed to the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents