The four tasks below must be completed in order (a single path of tasks) .Given the task information, what is the probability that the path of tasks will be completed in 20 days or less?
A) 34 days
B) 56.4%
C) 50%
D) 76.0%
Correct Answer:
Verified
Q23: Task X has a 82% probability of
Q24: Given the project plan shown below, which
Q25: Task X has a most likely duration
Q25: For a project with many task paths
Q26: Given the tasks, estimated durations, and crash
Q27: If a project path has an expected
Q29: Given the project plan shown below, for
Q30: Given the tasks, estimated durations, and crash
Q31: Given the tasks, estimated durations, and crash
Q32: Task X has a most likely duration