Given the Project Plan Shown Below, Which Task Has the Largest

Question 24

Multiple Choice

Given the project plan shown below, which task has the largest standard deviation (uncertainty) relative to its expected duration (standard deviation divided by expected duration) ? Given the project plan shown below, which task has the largest standard deviation (uncertainty)  relative to its expected duration (standard deviation divided by expected duration) ?   A) Task A B) Task B C) Task D D) Task G


A) Task A
B) Task B
C) Task D
D) Task G

Correct Answer:

verifed

Verified