Solved

Given the Project Plan Shown Below, for Each Task Assume

Question 29

Multiple Choice

Given the project plan shown below, for each task assume that the best case duration is 80% of the most likely duration, and the worst case duration is 150% of the most likely duration.What is the expected completion time for the critical path? Given the project plan shown below, for each task assume that the best case duration is 80% of the most likely duration, and the worst case duration is 150% of the most likely duration.What is the expected completion time for the critical path?   A) 34 days B) 21.0 days C) 35.7 days D) 22.1 days


A) 34 days
B) 21.0 days
C) 35.7 days
D) 22.1 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents