Figure 7-6 Network Scheduling Data

Question 43

Multiple Choice

  Figure 7-6 Network Scheduling Data -Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F?  A)  0  B)  15  C)  80  D)  107 Figure 7-6 Network Scheduling Data
-Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F? 


A)  0 
B)  15 
C)  80 
D)  107

Correct Answer: