Multiple Choice
Figure 7-4 Lab Experiment Project
-Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s) for this project?
A) A-C-F only
B) A-B-D-F only
C) A-B-E-F only
D) Both A-B-D-F and A-B-E-F are critical paths
Correct Answer:
Verified