Multiple Choice
Figure 7-4 Lab Experiment Project
-Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,how many days can you delay the calibration of the instrumentation (Activity B) ,without impacting the expected project completion date?
A) 0 days
B) 1 day
C) 2 days
D) 4 days
Correct Answer: