All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:
A) Add a significant buffer of time to each activity
B) Keep in mind time constraints such as learning curves, interruptions and competing priorities
C) Estimate times of completion of work without initial reference to a calendar
D) Verify all time estimates with the people doing the work
Correct Answer:
Verified
Q34: Creating a realistic schedule is often an
Q35: Q36: Which of these represents a typical problem that Q37: Q38: The schedule activity that determines when the Q40: This term is defined as the total Q41: All of the following statements correctly describe Q42: Describe free float and how you can Q43: Q44: Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents