Multiple Choice
Which of these represents a typical problem that can make it difficult to estimate activity durations accurately?
A) merging - multiple predecessors
B) checklists and templates
C) reducing sources of uncertainty in the estimate
D) carefully authorizing the start of non-critical activities
Correct Answer:
Verified