The Two Popular Scheduling Techniques Are ________

Question 66

Multiple Choice

The two popular scheduling techniques are ________.


A) Gantt charts and the Delphi method
B) Gantt charts and the jury of executive opinion method
C) Gantt charts and the program evaluation and review technique
D) the Delphi method and the program evaluation and review technique
E) the jury of executive opinion method and the program evaluation and review technique

Correct Answer: