The Following Questions Adapted from Tutorial Material of H Steyn

Question 29

Short Answer

The Following Questions adapted from tutorial material of H Steyn Ed., Project Management -A Multi-disciplinary Approach (Pretoria: FPM Publishing, 2003). Reprinted with permission.
-Complete the following table: state how the five steps of constraints management relate to the management of a single project when the critical chain method is used.
 Constraints  management step  Application to management of a (single) project  1. Identify the constraint  2. Decide how to exploit  the constraint(s)  3. Subordinate everything  to the decision(s) in 2 above  4. Elevate the  constraint(s) (in other  words, take steps to  "widen the bottleneck")  5. Go back to Step 1. \begin{array} { | l | l | } \hline \begin{array} { l } \text { Constraints } \\\text { management step }\end{array} & \text { Application to management of a (single) project } \\\hline \text { 1. Identify the constraint } & \\\hline \begin{array} { l } \text { 2. Decide how to exploit } \\\text { the constraint(s) }\end{array} & \\\hline \begin{array} { l } \text { 3. Subordinate everything } \\\text { to the decision(s) in } 2 \\\text { above }\end{array} & \\\hline \begin{array} { l } \text { 4. Elevate the } \\\text { constraint(s) (in other } \\\text { words, take steps to } \\\text { "widen the bottleneck") }\end{array} & \\\hline \begin{array} { l } \text { 5. Go back to Step 1. }\end{array} \\\hline\end{array}

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents