Statement: In the critical path method (CPM), the direct cost of an activity is assumed to be proportional to its time, so shortening it to its "crash" time reduces its cost.
Correct Answer:
Verified
Q15: GERT (circle all that are true):
A) utilizes
Q16: Statement: PERT requires three time estimates for
Q17: Statement: Given the assumptions of PERT, it
Q18: Statement: In PERT, the mean (expected) time
Q19: Statement: Although the times used in PERT
Q21: Statement: The cost slope is the marginal
Q22: Statement: Indirect costs include administrative, overhead, and
Q23: Statement: A "resource loading" chart shows the
Q24: Statement: In resource loading, the project schedule
Q25: Statement: It is relatively easy to level