GERT (circle all that are true) :
A) utilizes branching nodes
B) like PERT, cannot repeat activities
C) unlike PERT/CPM, allows for multiple possible outcomes in a project
D) like CPM, activity duration estimates are restricted to a single, deterministic estimate
Correct Answer: