An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs. Which of the following actions should the project manager take?
A) Submit a new change request.
B) Initiate the regression plan.
C) Add remediation to the schedule.
D) Accept the new power output.
Correct Answer:
Verified
Q43: Team members have reported that meetings are
Q44: A project manager who is part of
Q45: Due to a new government regulation, a
Q46: A vendor is unable to deliver an
Q47: A project manager received a change request,
Q49: A project manager needs to track the
Q50: A new project sponsor has joined the
Q51: A project has fallen behind schedule. Upon
Q52: A project manager noticed the development team
Q53: A project team is mainly based in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents