A Project Has Fallen Behind Schedule

Question 51

Multiple Choice

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?


A) Update the scope management plan.
B) Modify the project baselines.
C) Implement change control management.
D) Inform the stakeholders of the issue.