Question 41
Multiple Choice
A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?
Question 42
Multiple Choice
Which of the following is a schedule that illustrates the duration of an activity?
Question 43
Multiple Choice
Team members have reported that meetings are poorly attended and unproductive. Which of the following steps can the project manager take to make the meetings more productive?
Question 44
Multiple Choice
A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference. Which of the following is MOST likely to be the main challenge the influences this decision?
Question 45
Multiple Choice
Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well. The project manager should:
Question 46
Multiple Choice
A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager's NEXT steps? (Choose two.)
Question 47
Multiple Choice
A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?
Question 48
Multiple Choice
An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs. Which of the following actions should the project manager take?
Question 49
Multiple Choice
A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?
Question 50
Multiple Choice
A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority. Which of the following effects is this MOST likely to have on the project?
Question 51
Multiple Choice
A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?
Question 52
Multiple Choice
A project manager noticed the development team supporting a project does not have sufficient skills to complete the development phase. The project manager has discussed this issue with the functional manager and agreed to continue with the development phase due to time restrictions. Which of the following strategies is the project manager applying?
Question 53
Multiple Choice
A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable. Which of the following factors will MOST likely influence the communication methods used in the project?
Question 54
Multiple Choice
Which of the following describes how a project is related to a program?
Question 55
Multiple Choice
A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project's success?
Question 56
Multiple Choice
A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project. Which of the following would the project manager MOST likely do?