A Project Manager Needs to Track the Actual and Estimated

Question 49

Multiple Choice

A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?


A) Establish each WBS work package resource.
B) Establish and set the baseline.
C) Establish and set the quality gates.
D) Establish the tollgates.