There Are Four Parallel Paths on a Network Diagram

Question 17

Multiple Choice

There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks Which of the following tasks are on the critical path?


A) A, C, G
B) A, B, F
C) D, E, H
D) D, B, F

Correct Answer: