The project manager for a TV tower construction project receives notification that a strong storm is expected the following week. Which of the following should the project manager do NEXT?
A) Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.
B) Evaluate the risk, fill in the issue log, and communicate it according to the communication plan.
C) Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
D) Evaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.
Correct Answer:
Verified
Q8: A project requires daily status updates. Which
Q9: Which of the following are characteristics of
Q10: A stakeholder is unaware of a project's
Q11: During the initiation phase, a project manager
Q12: A project manager is unsure if the
Q14: One deliverable failed during testing, and this
Q15: A project manager is managing a project
Q16: A project sponsor and Chief Information Officer
Q17: There are four parallel paths on a
Q18: The executive sponsor asks a project manager
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents