Solved

During the Execution Phase of a Project, a Project Task

Question 21

Multiple Choice

During the execution phase of a project, a project task has run longer than anticipated. During the execution phase of a project, a project task has run longer than anticipated.   Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete? A)  12 days B)  14 days C)  16 days D)  19 days Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?


A) 12 days
B) 14 days
C) 16 days
D) 19 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents