Latest start time is calculated by
A) subtracting the activity's estimated duration from the activity's succeeding activity's latest finish time: LS = LF succeeding activity - estimated duration.
B) adding the activity's estimated duration to the predecessor of the activity's latest start time: LS = LS predecessor + estimated duration.
C) subtracting the activity's estimated duration from the activity's latest finish time: LS = LF - estimated duration.
D) adding the activity's estimated duration to the activity's latest finish time: LS = LF + estimated duration.
Correct Answer:
Verified
Q44: The ES and EF times are determined
Q45: Calculate the earliest finish for Task D
Q51: Calculate the latest start for Task D
Q52: With projects for which there is a
Q52: Latest start time (LS)is the latest time
Q55: Calculate the latest finish for Task B
Q56: Total slack for the project is the
Q58: Calculate the latest start for Task B
Q59: Earliest start time (ES)is the earliest time
Q60: Total slack is sometimes called
A)drift.
B)ride.
C)float.
D)sink.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents