Total slack for the project is the difference between
A) LF time of last activity and the project required completion time.
B) EF time of last activity and the project required completion time.
C) ES time of last activity and the project required completion time.
D) LS time of last activity and the project required completion time.
Correct Answer:
Verified
Q51: Calculate the latest start for Task D
Q52: Latest start time (LS)is the latest time
Q53: With projects for which there is a
Q54: Earliest finish time (EF)is the earliest time
Q55: Calculate the latest finish for Task B
Q57: Calculate the earliest start for Task B
Q58: Calculate the latest start for Task B
Q59: Earliest start time (ES)is the earliest time
Q60: Calculate the earliest finish for Task B
Q61: Free slack is calculated by finding the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents