Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.
A) day 8
B) day 7
C) day 12
D) Cannot be calculated based upon information given.