The ES and EF times are determined by calculating forward, that is, by
A) adding all the times together for the project.
B) working through the network diagram from the beginning of the project to the end of the project.
C) calculating the optimistic and pessimistic times for the project.
D) working through the network diagram from the end of the project to the beginning of the project.
Correct Answer:
Verified
Q39: Project management is a proactive approach to
Q40: When estimating resources for activities to estimate
Q41: In order to establish a basis from
Q42: Throughout the performance of the project, some
Q43: Calculate the latest finish for Task D
Q45: Calculate the earliest finish for Task D
Q46: The earliest start time for a specific
Q47: Latest finish time (LF)is the latest time
Q48: Latest start time is calculated by
A) subtracting
Q49: Total Slack is sometimes called
A) drift.
B) ride.
C)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents