In order to establish a basis from which to calculate a schedule using the estimated durations for the activities, it is necessary to
A) say who has responsibility for the first task.
B) enter the tasks into a project management information system.
C) select an estimated start time and a required completion time for the overall project.
D) edit the calendars for the resources in the project management information system.
Correct Answer:
Verified
Q36: Throughout a project, changes may occur that
Q37: When estimating the types and quantities of
Q38: People sometimes perform to expectations, their effort
Q39: Project management is a proactive approach to
Q40: When estimating resources for activities to estimate
Q42: Throughout the performance of the project, some
Q43: Calculate the latest finish for Task D
Q44: The ES and EF times are determined
Q45: Calculate the earliest finish for Task D
Q46: The earliest start time for a specific
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents