Question 42

Multiple Choice

Throughout the performance of the project, some activities will take longer than their estimated duration, others will be done in less time than their estimated duration, and


A) many will take no time to complete.
B) many will not be completed.
C) others are to be done by two project teams.
D) a few may conform to the estimated duration exactly.