Review the following schedule for a small project involving only two activities:
 Review the following schedule for a small project involving only two activities:     At the end of week two, progress information for Tasks A and B is as follows:   \begin{array} { | l | r | r | r | }  \hline &  { \text { PV } } & \text { AC } & \% \text { Complete } \\ \hline A & \$ 2,000 & \$ 1,000 & 50 \% \\ \hline \text { B } & \$ 2,000 & \$ 3,000 & 50 \% \\ \hline \end{array}   What can we conclude about the project at the end of week two?  A)  The critical path is behind schedule B)  Time estimate at completion EAC <sub>time</sub><sub>) </sub> )  = 5.625 months C)  EAC <sub>cost</sub><sub>) </sub> = $8,000 D)  CV% = -11.11% E)  A and D only F)  All of the above
At the end of week two, progress information for Tasks A and B is as follows:
 PV  AC % Complete A$2,000$1,00050% B $2,000$3,00050%\begin{array} { | l | r | r | r | } \hline & { \text { PV } } & \text { AC } & \% \text { Complete } \\\hline A & \$ 2,000 & \$ 1,000 & 50 \% \\\hline \text { B } & \$ 2,000 & \$ 3,000 & 50 \% \\\hline\end{array}
What can we conclude about the project at the end of week two?


A) The critical path is behind schedule
B) Time estimate at completion EAC time) ) = 5.625 months
C) EAC cost) = $8,000
D) CV% = -11.11%
E) A and D only
F) All of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents