What are possible values for earned value EV) , planned value PV) , and actual cost AC) if a project has an SPI of 0.5 and a CPI of 2.0?
A) EV = $30,000, PV = $60,000, AC = $15,000
B) EV = $60,000, PV = $30,000, AC = $15,000
C) EV = $15,000, PV = $30,000, AC = $60,000
D) EV = $60,000, PV = $15,000, AC = $30,000
E) None of the above
Correct Answer:
Verified
Q6: Which of the following is/are sources of
Q7: What is the difference between planned value
Q8: Which of the following offers the best
Q9: A project task is scheduled to begin
Q10: A project team has worked for six
Q11: Which of the following project monitoring tools
Q12: Given the following information about a project
Q13: Consider the following project circumstances. Assume the
Q14: Which of the following is important to
Q16: Review the following schedule for a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents