Consider the following project circumstances. Assume the information is accurate.
PV = $5,000,000
EV = $9,000,000
AC = $12,000,000
BAC = $15,000,000
Estimated Duration = 24 months
Elapsed Time To Date = 15 months
The project sponsor has called the PM into her office and asked the PM to resolve the most serious problem represented by the data shown above. Which of these options would be most appropriate and important for the PM to consider first in following the sponsor's request?
A) Crash critical path activities to compress the schedule.
B) Negotiate a later due date.
C) Add WBS items to match customer expectations
D) Work with suppliers to expedite deliveries and catch up on schedule delays
E) Check for scope creep
F) A and B only
Correct Answer:
Verified
Q6: Which of the following is/are sources of
Q7: What is the difference between planned value
Q8: Which of the following offers the best
Q9: A project task is scheduled to begin
Q10: A project team has worked for six
Q11: Which of the following project monitoring tools
Q12: Given the following information about a project
Q14: Which of the following is important to
Q15: What are possible values for earned value
Q16: Review the following schedule for a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents