The output that results from breaking down a product into the individual components is called:
A) work decomposition.
B) product decomposition.
C) product breakdown structure.
D) work breakdown structure.
Correct Answer:
Verified
Q6: A start- to- start dependency indicates that:
A)the
Q7: A finish- to- start dependency indicates that:
A)the
Q8: Budgetary estimates can vary by as much
Q9: _is a scheduling technique that requires greater
Q10: The diagramming method using boxes and rectangles
Q12: The process of developing a network diagram
Q13: A WBS dictionary:
A)is part of the project
Q14: Using a bottom- up approach for creating
Q15: _dependencies indicate the relationship of activities that
Q16: Network_ are templates developed from previous projects