The process of developing a network diagram and updating the activity list from the activity definition phase is called:
A) activity sequencing.
B) activity ordering.
C) activity definition.
D) activity scheduling.
Correct Answer:
Verified
Q7: A finish- to- start dependency indicates that:
A)the
Q8: Budgetary estimates can vary by as much
Q9: _is a scheduling technique that requires greater
Q10: The diagramming method using boxes and rectangles
Q11: The output that results from breaking down
Q13: A WBS dictionary:
A)is part of the project
Q14: Using a bottom- up approach for creating
Q15: _dependencies indicate the relationship of activities that
Q16: Network_ are templates developed from previous projects
Q17: _is the time delay between completion of