The diagramming method using boxes and rectangles connected by arrows to represent activities and their dependencies in a project is called:
A) conditional diagramming method.
B) arrow diagramming method.
C) box plot.
D) precedence diagramming method.
Correct Answer:
Verified
Q5: _is the process of identifying and defining
Q6: A start- to- start dependency indicates that:
A)the
Q7: A finish- to- start dependency indicates that:
A)the
Q8: Budgetary estimates can vary by as much
Q9: _is a scheduling technique that requires greater
Q11: The output that results from breaking down
Q12: The process of developing a network diagram
Q13: A WBS dictionary:
A)is part of the project
Q14: Using a bottom- up approach for creating
Q15: _dependencies indicate the relationship of activities that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents