A start- to- start dependency indicates that:
A) the completion of the successor activity depends on the beginning of the predecessor.
B) a second activity cannot be started until the first activity has been completed.
C) the start of a successor depends on the start of the predecessor.
D) the completion of the successor activity depends on the completion of the predecessor.
Correct Answer:
Verified
Q1: Order of magnitude estimates can vary by
Q2: A progressively more detailed and accurate projection
Q3: What is NOT among the top- five
Q4: The lowest- level deliverables in a work
Q5: _is the process of identifying and defining
Q7: A finish- to- start dependency indicates that:
A)the
Q8: Budgetary estimates can vary by as much
Q9: _is a scheduling technique that requires greater
Q10: The diagramming method using boxes and rectangles
Q11: The output that results from breaking down
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents