A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Goldratt's model to determine the aggregated buffer for this project.
A) 20 days
B) 10 days
C) 15 days
D) 5 days
Correct Answer:
Verified
Q71: A project is represented by the activity
Q72: A project consists of four consecutive tasks
Q73: A project is represented by the activity
Q74: A project consists of four consecutive tasks
Q75: A project is represented by the activity
Q77: A project consists of four consecutive tasks
Q79: A project is represented by the activity
Q80: Subcontractor deliveries are difficult to schedule with
Q80: A project is represented by the activity
Q81: A project that consists of six consecutive
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents