A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the feeder buffer if this project is managed using critical chain methodology?
A) 9.0
B) 7.5
C) 4.5
D) 6.0
Correct Answer:
Verified
Q64: CCPM advocates performing all non-critical activities:
A)As late
Q67: A project consists of six consecutive tasks
Q68: A project is represented by the activity
Q69: A project is represented by the activity
Q72: A project consists of four consecutive tasks
Q73: A project is represented by the activity
Q74: A project consists of four consecutive tasks
Q75: A project is represented by the activity
Q76: A project consists of four consecutive tasks
Q77: The buffers supplied to non-critical paths in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents