A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology?
A) 4.5
B) 11.5
C) 20.5
D) 16
Correct Answer:
Verified
Q64: CCPM advocates performing all non-critical activities:
A)As late
Q68: A project is represented by the activity
Q69: A project is represented by the activity
Q71: A project is represented by the activity
Q72: A project consists of four consecutive tasks
Q74: A project consists of four consecutive tasks
Q75: A project is represented by the activity
Q76: A project consists of four consecutive tasks
Q77: A project consists of four consecutive tasks
Q80: Subcontractor deliveries are difficult to schedule with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents