A project is represented by the activity durations (estimated at 90% likelihood of completion) and precedence requirements shown in the table. What is the length of the project buffer if this project is managed using critical chain methodology?
A) 13.5
B) 22.5
C) 11.25
D) 9.0
Correct Answer:
Verified
Q75: A project is represented by the activity
Q76: A project consists of four consecutive tasks
Q77: A project consists of four consecutive tasks
Q79: A project is represented by the activity
Q80: Subcontractor deliveries are difficult to schedule with
Q81: A project that consists of six consecutive
Q82: Use the project information in the table
Q84: Drum buffers are:
A)A safety margin separating different
Q88: Define and describe the function and interrelationship
Q97: When choosing the most viable solution to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents