An activity has a pessimistic time that is three times as long as its most likely time and five times as long as its optimistic time.If the activity variance is 10,what is the expected time?
A) about 10 days
B) about 14 days
C) about 19 days
D) about 23 days
Correct Answer:
Verified
Q24: The variance of an activity is given
Q37: A sequence of activities defined by the
Q38: _ activities can be used as summaries
Q39: There is no slack on the project
Q40: One of the defining points of a
Q43: Ray's shipment of materials hit every red
Q44: The length of time expected to complete
Q45: What is the late start time for
Q46: An activity has an optimistic time estimate
Q47: Based on the activity network pictured,what is