The length of time expected to complete an activity assuming that its development proceeds normally is called the:
A) optimistic duration.
B) pessimistic duration.
C) most likely duration.
D) normal duration.
Correct Answer:
Verified
Q24: The variance of an activity is given
Q39: There is no slack on the project
Q40: One of the defining points of a
Q42: An activity has a pessimistic time that
Q43: Ray's shipment of materials hit every red
Q45: What is the late start time for
Q46: An activity has an optimistic time estimate
Q47: Based on the activity network pictured,what is
Q48: An activity has an optimistic time estimate
Q49: What is the early start time for