Multiple Choice
The variance of an activity is given by:
A) [1/6(b-a) ]2.
B) 1/6[b-a].
C) [1/36(b-a) ]2.
D) 1/36[b-a].
Correct Answer:
Verified
Related Questions
Q7: Concurrent activities are:
A)Activities that must be done
Q20: Q21: Preceding activities are those that must occur Q22: Project Test Bank is composed of Q22: An activity has an optimistic time estimate Q25: Project Test Bank is composed of Q26: At a merge point in a forward Q32: An activity has an optimistic time estimate Q35: What are hammock activities and when should Q39: A merge activity has two or more