Which statement about critical chain methodology is best?
A) Activity durations estimated at a 50% level of successful completion are shorter than those estimated at a 90% level of successful completion.
B) Aggregated activity durations at a 90% level of successful completion are shorter than aggregated activity durations at a 50% level of successful completion.
C) The total safety buffer for aggregated activity durations is smaller than the sum of safety buffers for individual activity durations at any likelihood level estimate.
D) None of these statements is correct.
Correct Answer:
Verified
Q34: Which of the following is an example
Q44: All five members of a project team
Q45: The student syndrome of wasting extra safety
Q45: A project consists of four consecutive tasks
Q47: Your next project consists of 10 consecutive
Q47: A project consists of three activities with
Q47: A worker is assigned three tasks,A,B,and C,each
Q48: A complex project concludes with three paths
Q55: Under the student syndrome model,the slope of
Q59: A worker is assigned three tasks,A,B,and C,each
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents