Which of the following is an example of special cause variation?
A) Yesterday the framing crew was a little tired and didn't get as much done as they thought.
B) The avian flu ravaged the laying stock for Chickenverks and the Great Egg Shortage of '06 threatened to cancel Easter egg hunts worldwide.
C) The product unveiling was a week late because there was some difficulty getting the ivory through customs.
D) The debugging step averages two months but this project was finished a day early.
Correct Answer:
Verified
Q29: Project personnel often become involved in several
Q30: Keith welds a one-fourth-inch diameter ball bearing
Q31: Critical Chain Project Methodology _ risk for
Q32: ABC project organization has one workstation that
Q33: The best thing a project manager can
Q35: Which of the following is an example
Q36: The first step in TOC methodology is
Q37: CCPM advocates putting off non-critical activities as
Q38: The _ syndrome describes the tendency to
Q39: In applying the principle of common cause
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents