A complex project concludes with three paths merging into a final activity,after which the project is completed.Two of these paths are non-critical and have been managed effectively,with slack remaining.The critical path has also been managed well and is on time entering the merge node.Which statement is best?
A) The merge activity will eliminate the positive slack.
B) The slack will remain with the project unless the final activity is delayed.
C) The critical path method accounts for path convergence.
D) The critical path method tends to overestimate project durations.
Correct Answer:
Verified
Q43: All five members of a project team
Q44: All five members of a project team
Q45: The student syndrome of wasting extra safety
Q46: The Central Limit Theorem says that if
Q47: A worker is assigned three tasks,A,B,and C,each
Q49: Which of these is Parkinson's Law?
A)Don't put
Q50: In order to estimate completion of a
Q51: A worker is assigned three tasks,A,B,and C,each
Q52: A worker is assigned three tasks,A,B,and C,each
Q53: Which tendency is NOT a contributing factor
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents