A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table. Use Newbold's model to determine the aggregated buffer of one standard deviation for this project.
A) 31 days
B) 16 days
C) 8 days
D) 5 days
Correct Answer:
Verified
Q43: Which statement about critical chain methodology is
Q44: All five members of a project team
Q47: Your next project consists of 10 consecutive
Q47: A project consists of three activities with
Q47: A worker is assigned three tasks,A,B,and C,each
Q48: A complex project concludes with three paths
Q49: A project consists of four consecutive tasks
Q52: A worker is assigned three tasks,A,B,and C,each
Q55: Under the student syndrome model,the slope of
Q59: A worker is assigned three tasks,A,B,and C,each
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents