Schedule control has four steps, they are
A) accelerate tasks on critical path, analyze the schedule, calculate the schedule, identify the next task to fast track.
B) meet with the project team, listen to schedule reports, update the schedule, revise the plan.
C) identify any problems, follow the nine-step problem solving approach, apply the solution, update the schedule.
D) analyze the schedule, decide actions, revise plan, recalculate the schedule.
Correct Answer:
Verified
Q117: When changes are agreed upon, a new
Q118: The duration of a task is
A) the
Q119: The earliest start time for an activity
Q120: The _ is the estimated cost to
Q121: Schedule updates of the project using actual
Q122: The actual finish time of an activity
A)
Q123: If the project needs accelerated, efforts should
Q125: Each time the schedule is recalculated in
Q126: If the project is ahead of schedule,
Q127: The key to effective project control is
A)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents