Each time the schedule is recalculated in the project, the schedule should be
A) analyzed to see if it needs further adjustment.
B) accelerated on all paths with a positive slack.
C) examined for a change in critical paths then fast track the new critical path.
D) examined and assign additional resources to the activities with free slack.
Correct Answer:
Verified
Q117: When changes are agreed upon, a new
Q118: The duration of a task is
A) the
Q119: The earliest start time for an activity
Q120: The _ is the estimated cost to
Q121: Schedule updates of the project using actual
Q122: The actual finish time of an activity
A)
Q123: If the project needs accelerated, efforts should
Q124: Schedule control has four steps, they are
A)
Q126: If the project is ahead of schedule,
Q127: The key to effective project control is
A)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents