If the project is ahead of schedule, then concentrated efforts should be made to
A) allow the tasks to start on the days estimated as the earliest start time in the baseline plan.
B) fast track the critical path activities.
C) reduce the number of resources on the project because they are not needed.
D) keep it ahead of schedule.
Correct Answer:
Verified
Q117: When changes are agreed upon, a new
Q118: The duration of a task is
A) the
Q119: The earliest start time for an activity
Q120: The _ is the estimated cost to
Q121: Schedule updates of the project using actual
Q122: The actual finish time of an activity
A)
Q123: If the project needs accelerated, efforts should
Q124: Schedule control has four steps, they are
A)
Q125: Each time the schedule is recalculated in
Q127: The key to effective project control is
A)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents