The actual finish time of an activity
A) is always less than the estimated duration.
B) has a ripple effect in the project and may alter the remaining activities' earliest start and finish times.
C) has no impact on the critical path of the project.
D) is used to calculate the latest start and finish times of the remaining activities in the project.
Correct Answer:
Verified
Q117: When changes are agreed upon, a new
Q118: The duration of a task is
A) the
Q119: The earliest start time for an activity
Q120: The _ is the estimated cost to
Q121: Schedule updates of the project using actual
Q123: If the project needs accelerated, efforts should
Q124: Schedule control has four steps, they are
A)
Q125: Each time the schedule is recalculated in
Q126: If the project is ahead of schedule,
Q127: The key to effective project control is
A)
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents