Five jobs are waiting for processing through two work centres.Their processing time (in minutes) at each work centre is contained in the table below.Each job requires work centre Sigma before work centre Delta.According to Johnson's rule,what sequence of jobs will minimize the completion time for all jobs?
A) R-S-T-U-V
B) S-V-T-R-U
C) S-U-T-V-R
D) V-R-U-S-T
E) none of the above
Correct Answer:
Verified
Q61: Conventional MRP uses time buckets that do
Q63: Which of the following dispatching rules is
Q64: Sequencing (or dispatching)
A) assigns dates to specific
Q66: Eight jobs have been sequenced at a
Q69: Which of the following is an advantage
Q72: When a set of jobs must pass
Q77: Five jobs are waiting for processing through
Q78: Five jobs are waiting to be processed.Their
Q78: Flow time represents the time
A) an order
Q120: _ uses computerized short-term scheduling to overcome
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents