Each activity in a network diagram is represented by a box in the ____, and the ____ of the activity is written within the box.
A) work breakdown structure, name
B) network diagram, description
C) project scope document, responsible organization
D) responsibility assignment matrix, name of the responsible person
Correct Answer:
Verified
Q105: Standard subnetworks should be developed for those
Q106: A network diagram is a tool for
Q107: The _ is a roadmap that displays
Q108: To draw a _, start by drawing
Q109: _ contains a small number of higher-level
Q111: Activities should _ the time intervals at
Q112: Arrows linking the activity boxes in a
Q113: In preparing a network diagram, drawing activities
Q114: Designating _ as having primary responsibility can
Q115: The description of an activity in a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents